Industrial Training

18 July 9 September

Intro
duction

Industrial Training

18 July 9 September

Industrial Training

18 July 9 September

UP Brantas
PLTA NGEBEL

PLTA MENDALAN

PLTA SIMAN

PLTA WONOREJO

PLTA SUTAMI
PLTA GIRINGAN

JAWA
WEST
CENTRAL

MADURA
EAST
D

PLTA SENGGURUH

E C BA
BALI

PLTA WLINGI

PLTA TULUNGAGUNG

PLTA SELOREJO
PLTA GOLANG

PLTA WONOREJO
PLTA LODOYO

UP Brantas

Lahor Dam

Waduk Selorejo

Waduk Sutami

Waduk Wonorejo

Waduk
Tulungagung

Waduk Lodoyo

Waduk Sengguruh

Waduk Wlingi

PLTA
(MW)
Sengguruh
Sengguruh
Sutami
Sutami
Sutami
Wlingi
Wlingi
Lodoyo
Tulungagung
Tulungagung
Selorejo
Mendalan
Mendalan
Mendalan
Mendalan
Siman
Siman
Siman
Giringan
Giringan
Giringan
Golang
Golang
Golang
Ngebel

Industrial Training

UNIT POWER
RATA-2/TH
1
2
1
2
3
1
2
1
2
1
2
3
4
1
2
3

1
2
3
1

14,50
14,50
35,00
35,00
35,00
27,00
27,00
1
18,00
18,00
1
5,60
5,80
5,80
5,80
3,60
3,60
3,60
1
2
3
0,90
0,90
0,90
2,20

PRODUKSI kWH

77.846.000
465.302.000
143.000.000
4,50
36.740.000
117.500.000
4,48
25.264.000
81.510.000

55.000.000
0,90
11.850.000
0,90
1,40
9.000.000
8.000.000

18 July 9 September

Definition of Hydroelectric
Plant
Hydroelectric Plant facility
that specific equipment and
purpose to change the
(conversion) potential
energy of water into
electrical energy
Industrial Training

18 July 9 September

Working
Principle

Industrial Training

18 July 9 September

Working Principle Of Hydroelectric

Potential
Energy
Gravitationa
l
PE = mgh

Kinetic
Energy
Rotational
KE = 0.5 m
V

Industrial Training

Mechanical
Energy

Electricity
Energy

Turbine work for


Potential Energy
TME = PE + KE

Generator with
Electromagnetic
force principle

18 July 9 September

Electric Power
Electric power generated can be calculated using this
formula:

P = 9.8 Q h T G
(kw)
Q
= water flow
h

= height

= efficiency of turbine

G = efficiency of generator

Industrial Training

18 July 9 September

Process

Industrial Training

18 July 9 September

1.
2.
3.
4.
5.
6.
7.
8.

Dam
Water Intake
Dam Control Centre
Headrace Tunnel
Penstock
Surge Tank
Inlet Valve
Spiral Case

Industrial Training

18 July 9 September

Hydroelectric SUTAMI

Industrial Training

18 July 9 September

Schematic Hydroelectric

Industrial Training

18 July 9 September

Main
Component

Industrial Training

18 July 9 September

Dam
Type

: Rock Fill

Length width

: 810 m

Peak width

: 13.7 m

High

: 100 m

Base width

: 400 m

Volume

: 6.156.000 m

Max. capacity

: 343.000.000
m

Effective
capacity

: 253.000.000
m

Submerged
area

: 15 km

Stream

: 2.050 km

Elevation HWL : 272.50

Industrial Training

18 July 9 September

Turbine
Brand

: Toshiba

Type

: Francis
Vertical

Head Max.

: 93.50 m

Head Min

: 60.50 m

Head Effective : 85.40 m


Discharge

: 53.50 m3/det

Industrial Training

18 July 9 September

Generator

Industrial Training

Brand

: Toshiba

Type

: Semi
Umbrella

Capacity

: 39 MVA

Power Factor

: 0.90

Speed

: 250 rpm

18 July 9 September

Main Transformer
Type

: DA/FA (self
cooler)

Average
Capacity

: 19.500 KVA

Max. Capacity

: 39 KVA

Frequency

: 50 Hz

Primary
Voltage

: 11 KV

Secondary
Voltage

: 154 KV

Impedance

: 4.87 or 9.73 %

Cooling type

: ONAN/ONAF

Temperature
Rise

: 50C

Industrial Training

18 July 9 September

What
Transformer
is
s?
Industrial Training

18 July 29 August 20

Main
Transformers

Types of
Transformers
11KV to 154 KV
50 Hz
Delta - Star
ONAN/ONAF

Industrial Training

18 July 29 August 20

Local Service
Transformers

Types of
Transformers
11KV to 6 KV
50 Hz
Delta - Delta
ONAN

Industrial Training

18 July 29 August 20

Station Service
Transformers

Types of
Transformers
6 KV 220/380v
50 Hz
Delta - Star
ONAN

Industrial Training

18 July 29 August 20

Protection
System

Requirements for protection


system
1. Selective & Discrimination
2. Stability
3. Speed
4. Sensitive
5. Economy
6. Reability
7. Protection support (Backup)

Industrial Training

18 July 29 August 20

Protection
System

Components of Protection
System
1. Circuit breaker
2. Relay
3. Current Transformers
4. Potential Transformers
5. Cable control
6. Uninterruptible power supply (UPS)

Industrial Training

18 July 29 August 20

Than
You
k

Industrial Training

18 July 9 September

You might also like