Digi Refarming Project Org Chart

Project Sponsor

Project Owner

Sivakumar

Jaime Chee Kar


Yean

Digi-Privatel Refarming 2.0 Update


(Southern+Eastern 900MHz)
14-Sep 2016

13 July 2016 Private and Confidential

Organization Structure for Refarming Implementation &


Optimization

3 March 2016 Private and Confidential

Southern & Eastern 900MHz Refarming Progress Update

22-28Aug:
Completed MR collection (18-24Aug)
Done TRX cut analysis
Done overshooting analysis
Completed neighbour optimisation analysis
Baseline collection

12-18Sep:
2nd Mr collection (12Sep)

Refarming

29-9Sep:

Baseline wk33

Eastern 25x26 Sep


Southern 29x30 Sep

TRX cut scripting and execution


NBR optimisation
Cell Shaping

MR collection wk33

AFP (19 Sep)

We are here

3 March 2016 Private and Confidential

Post Opti

Summary of Pre Refarming Opti


TRX cut

587 TRX cut performed which represent 16.5% of total TRX in Eastern & Southern
region.
SDCCH signaling channel re-dimensioned to allow more traffic channel for TRX cut.
943 out of 2063 SD channel cut. No SD blocking observed.

Neighbour Analysis
Based on one week HO stats coincide with MR collection
2688 redundant NBR relation deleted.

Cell shaping
Based on MR and TA analysis, 11 worst cells performed cell shaping to reduce interference
to adjacent cell for better frequency plan.

3 March 2016 Private and Confidential

Frequency Planning Plan and Status

MR data collection 12/09-19/09 ongoing

30KM border RRU scan and interfered frequencies identification done

AFP starts on 19/09 identify worst offenders and resolve conflicts:


Eastern: 19/09-22/09
Southern: 23/09 & 27-29/09

Script preparation and validation:


Eastern: 23/09
Southern: 29/09

After the refarming implementation:


Worst cells routines: Eastern 26/09 & Southern 30/09

Implementation
Implementation on 25x26 September for Eastern and 29x30 September for Southern
Divided team into night team and day team for 24 hours babysitting
Night Team

Day Team

PM -Loh

PM -Ashraf

Opti Expert - Praveen

Senior Opti - Andrew

Script/RAN - Selva

Script/RAN - Kamal

OSS Aman + Shashank

OSS Kamal + Nazreen

DT x 2 teams

Planner - Milen

Refarming flow:
Preload script (refarm &
fallback) and validate
Close KPI
monitoring/Babysitting

KPI degardation
>50% ?

No
Refarming start

Yes

Troubleshot and
normalised on the spot

Yes
No

Alarm Monitoring

Post Refarming Optimisation

3 March 2016 Private and Confidential

Fallback

Risk and Mitigation


Risk

Mitigation

1. HOSR degradation

Avoid re-farming with TRX blocked

2. Interference from Thailand


DTAC

Perform RRU scanning for sites at Thai order


and prioritise clean frequency for sites being
interfered

3. Script run error

Script (including fall back script) to be


preloaded in Netnumen and validated before
execution.

4. KPI monitoring delay

2 x OSS KPI engineer ready for execution and


day time monitoring. Pre-prepared ploting
template ready for efficient KPI update

5. Other KPI degradation

Close KPI monitoring


Principle ZTE engineer on site support
DT validation
Fall back on last resort

Drive Test Verification

Test

Method/Remark

1. Static
(Verification)

2. Mobility

Location

Resource

Voice
SMS
Whatsapp
Speed Test (Ookla)
Immediately Post
Refarm

1. Eastern

2 x Drive Test
Team Per
Region

UE 1 Short Call
Dual Mode + UE2
Long Call (2G
Mode)

1. Eastern Cluster Kota


Bharu, Kuantan.
2. Southern Cluster Melaka,
Johor Bharu
(Both at G900
Location/Outskirt)

Kuantan 8527A, 8526A


Kota Bharu 8257A, 8258A

2. Southern

Johor 6992A, 6115A, 6096A

2 x Drive Test
Team Per
Region

Thank You

3 March 2016 Private and Confidential