Professional Documents
Culture Documents
Engineering - Wind
Offshore Wind Farms
Turbine Selection
Substructure definition
Electrical Definition
Cable Design
Shore Approach
Transformer Platform
Installation methods
Cost Estimate
Project Schedule
Contract & specification preparation
Comparative Assessment
Assess structural integrity
Scoring system :
Design/Plan Risk
Fabrication Risk
Installation Risk
OPEX Risk
Other Risks
30%
30%
30%
5%
5%
100%
Options Selection
Factors Against
Ground not suitable due to large ratio of overturning
moment to vertical self weight.
Use of ballast to increase weight and stability might lead to
uneven settlements out of tolerance with requirements.
Large infrastructure set up cost
Factors Against
On the limit of fabrication and installation abilities at
shallower end of water depth due to high wind loading.
Probably impossible at deeper end of farm. Not suitable for
these water depths and soil conditions.
Specialist hammers may need to be procured from Europe
increasing cost
Installation Noise
7
10
Options Selection:
Jacket Pile through Legs
Factors in Favour
Conventional Gulf of Mexico design,
proven methodology
Factors Against
Difficult to install together with the
transition piece
Long piles
Mudmats required
Can be heavier than pre-piled jacket
11
Factors Against
Mudmats and extraneous sleeve
support structure not required after
installation
Relies on the integrity of the connection to remain safe
during life
12
Factors Against
Savings on extraneous items not used after
installation.
Inspection required for setting shimming level to
prevent tilting
13
Foundation Installation
14
15
16
Options Selection:
Jacket With Suction Caissons
Factors in Favour
Installation cost saving
Used in oil & gas
Factors in Against
Novel approach
Some difficulty possible in
ensuring the caissons are installed
in required positions
Suction insertion may not be possible
Depends on soil conditions and water depth
17
19
Figuratively representative
transition piece, patent
applied
VIDEO
20
21
Ormonde: Jackets
30 x 5MW WTG
1 x Substation Platform
Conceptual Design
FEED
SSP Jacket & Deck Design
Project Management
Services
22
23
Ormonde - Installed
24
25
26
27
Ormonde
Greater Gabbard
Gwynt-Y-Mor
UK Offshore
ODE Responsibility
Detailed Design
Fabrication Support
Offshore Sub-Station
Self Installing Substation
MOAB Type - Self-Installing
Capacity Solution to 800 MW
28
29
30
31
32
33
34
35
36