PROBLEM 1
Given
Job 1 2 3 4 5 6
Machine 8 10 11 12 16 20
A
Machine 7 15 10 14 13 9
B
Sequence
Job 2 3 4 5 6 1
MACHINE A MACHINE B
Continue
Total Elapsed time
Machine A Machine B
Sequ Start Add Time End Start Add Time End
ence time taken time time taken time
2 0 + 10 10 10 + 15 25
3 10 + 11 21 25 + 10 35
4 21 + 12 33 35 + 14 49
5 33 + 16 49 49 + 13 62
6 49 + 20 69 69 + 9 78
1 69 + 8 77 78 + 7 85
Total 77 68
Time
Job sequence:
Job 5 3 1 2 4
Other Possible Sequences
Job 5 4 1 2 3
Job 5 4 1 3 2
Continue
Total Elapsed time
Machine A Machine B Machine C
Sequ Start Time End Start Time End Start Total End
ence time taken time time taken time time time Time
5 0 6 6 6 2 8 8 8 16
3 6 8 14 14 5 19 19 4 23
1 14 10 24 24 6 30 30 9 39
2 24 11 35 35 4 39 39 5 44
4 35 7 42 42 3 45 45 6 51
TOTAL 42 20 29
TIME
Continue
Idle Time for M/c A=
Total Elapsed Time- Total time of M/c A
51-42=9 hrs.
Idle Time for M/c B=
Total Elapsed Time- Total time of M/c B
51-20=31hrs.
Idle Time for M/c C=
Total Elapsed Time- Total time of M/c B
51-29=22hrs.
Total Elapsed time=51 hrs
PROBLEM 3
Given
Job M1 M2 M3 M4
A 13 8 7 14
B 12 6 8 19
C 9 7 5 15
D 8 5 6 15
Step 1- 1st we have to convert this problem into two machine problem. For
that we have to check following condition:
Min M1 or Min M4 >= Max M2 or Max M3
here Min M1=8, Min M4=14, Max M2=7, Max M3=8.
therefore 8=8
Min M1=Max M3
Continue
Consolidation or Conversion Table
JOB MACHINES 5 MACHINES 6
P(M1+M2+M3) NEW TIME P(M2+M3+M4) NEW TIME
A 13+8+7 28 8+7+14 29
B 12+6+8 26 6+8+19 33
C 9+7+5 21 7+5+15 27
D 8+5+6 19 5+6+15 26
Job sequence:
JOB D B A C
Elapsed time calculation
Machine 1 Machine 2 Machine 3 Machine 4
S.Q ST TT ET ST TT ET ST TT ET ST TT ET
D 0 8 8 8 5 13 13 6 19 19 15 34
B 8 12 20 20 6 26 26 8 34 34 19 53
A 20 13 33 33 8 41 41 7 48 53 14 67
C 33 9 42 42 7 49 49 5 54 67 15 82
T.T 49 26 26 63