You are on page 1of 23

Project Report Presentation

Six Sigma

Project Number: 01

Project Name: To reduce the TAT for ISI for a file from 1.30
Hours to 50 Minutes to increase the Per day
production from 6 files to 8 files by January
2017.

Project Team Leader: Harish Kumar J


Six Sigma Roadmap
Define

Measure

Analyze

Improve

Control
Problem and Goal

Problem Statement:

For the past 6 months we were able to delivery around 175 to 180 output file
in a week. The current TAT for a file is at 1.30 hours. With the current TAT,
achieving the target requires additional manpower with in turn affects the
revenue. The reduction in the TAT will increase revenue, reduce cost and
increase customer satisfaction.
y = f(x) - y is the TAT and the x are causes for the delay or the higher TAT.

Goals/Objective(s):

1. To reduction in the TAT by 40% and increase the delivery count by 50%.

2. Reduction of resources from 8 to 6 by the end of Jan-2017.


Project Scope

In Scope:
Process Start Point Updates in the MCA website.
Process Stop Point Delivery of the final Output.

Items Out of Scope:


Quality Check is not included into the productivity
Dependency on the source for input availability
Project Team Membership

Project Champion:
Babu/PGS/Pradeep

Project Team Leader:


Harish Kumar

Project Core Team Members:


Krishna Kumar
Anitha

Priyanka

Maqbool Basha
Project Plan- Milestones and Timing

Name of Phase Target Completion Actual Completion


Date Date
Define Phase 04th Nov 2016 04th Nov 2016
Measure Phase 25th Dec 2016
Analyze Phase 1st Feb 2017
Improve Phase 15th Feb 2017
Control Phase 15th Mar 2017
Project Closing 31st Mar 2017
Voice of Customer to CTQ Analysis

Customer Voice of the Customer CTQ(the Y)

ISI Frenquently Check for financial updates TAT

ISI Consistent weekly delivery count TAT

ISI Error-free financials Quality


High Level Process Map (SIPOC)

Supplier Input Process Output Customer


ISI (EMIS) List of Check the existence of Financial ISI (EMIS)
companies company report in excel
Annual report of Check the asset and
companies from revenue details of the
MCA company
Balance sheet of Obtain the company
companies from information from annual
MCA report, website and other
sources
Obtain the financials from
balance sheet & Profit &
loss
Update the same in the
excel
Six Sigma Roadmap
Define

Measure

Analyze

Improve

Control
Project Y (or Ys) in Y=f(x)
TAT Time taken by a user to complete one financial.
Detailed Process Map
Plan for Data Collection
What to Measure
Productivity Target
Productivity Achieved
Time taken

Data Collection Template


Graphical Analyses
Potential Xs
X1: Type of input financials

X2: User Skills

X3: Higher non productivity hours


Cause-Effect Diagram(s)
Six Sigma Roadmap
Define

Measure

Analyze

Improve

Control

Project Report Template 17 .PPT


Potential XsTheories To Be Tested
X1: Analyzing the variation between the TAT for different
input types

X2: Analyzing the variation between users

X3: Analyzing to reduce the non productive hours


Data Collection Plan for Analyze Phase

Project Report Template 19 .PPT


Example: for Each Test of
Theory:

H :Theories
H:
o

Analysis:

Statistical Conclusion:
Practical Conclusion:

Project Report Template 20 .PPT


Six Sigma Roadmap
Define

Measure

Analyze

Improve

Control

Project Report Template 21 .PPT


Six Sigma Roadmap
Define

Measure

Analyze

Improve

Control

Project Report Template 22 .PPT


Project Results

Project Baseline: Project Target: Project Actual:

COPQ= COPQ= COPQ=

Metric= Metric= Metric=

DPMO= DPMO= DPMO=

Sigma Sigma Sigma


Level= Level= Level=

Project Report Template 23 .PPT


Lessons Learned

Project Report Template 24 .PPT