You are on page 1of 35

Project Management

Dr. Pawan K. Taneja


Indian Institute of Public Administration (IIPA)
New Delhi
Ingredients of Project

Specific outcomes: Products or


results

Definite start and end dates:


Projects don’t go on forever

 Established budgets: Required


amounts of people
Project Management

• Used to manage large complex projects

Has three phases:


1. Project planning
2. Project scheduling
3. Project controlling
Phase 1: Project Planning

1. What is the project goal or objective?


2. What are the activities (or tasks) involved?
3. How are activities linked?
4. How much time required for each activity?
5. What resources are required for each
activity?
Phase 2: Project Scheduling

1. When will the entire project be


completed?
2. What is the scheduled start and end time
for each activity?
3. Which are the “critical” activities?
4. Which are the noncritical activities?
Phase 2: Project Scheduling (cont.)

5. How late can noncritical activities be w/o


delaying the project?
6. After accounting for uncertainty, what is
the probability of completing the project
by a specific deadline?

When do you want the


Project to be
done?
Phase 3: Project Controlling

At regular intervals during the project the


following questions should be considered:

• Is the project on schedule? Early? Late?


• Are costs equal to the budget? Over
budget? Under budget?
• Are there adequate resources?
• What is the best way to reduce project
duration at minimum cost?
Project Scheduling Phase

Commonly used techniques:

• Gantt Chart (Bar Chart)


• Critical Path Method (CPM)
• Evaluation and Review Technique
(PERT)
Gantt Chart

• Graph or bar chart with a bar


for each project activity that
shows passage of time
• Provides visual display of
project schedule
Historical Background
CPM (Critical Path Method) scheduling was developed in the late
1950's.

Introduced to the industry as a tool to improve planning and scheduling of


construction programs.

Concurrent with industrial development of CPM, the U.S. Navy introduced


a similar method of scheduling called PERT.

PERT is an acronym for Program Evaluation and Review Technique.

The Navy developed this method to evaluate and monitor progress of the
Polaris Missile Program.

The major difference between CPM and PERT is that PERT is a more
probabilistic approach that lends itself to activities for which there is little or
no historical experience, whereas CPM uses historical information for
establishing durations.
Demonstration
A house is to be constructed. The various activities are listed in the following table
with an information on time and predecessors.

Sr. No. Activity Duration(months) predecessor


1 Design house and obtain 3
financing
2 Lay foundation 2 1
3 Order and receive 1 1
materials
4 Build house 3 2,3
5 Select paints 1 2,3
6 Select carpet 1 5
7 Finish work 1 6
Example of Gantt Chart
Month
0 | 2 | 4 | 6 | 8 | 10
Activity
Design house
and obtain
financing
Lay foundation
Order and
receive
materials

Build house

Select paint

Select carpet

Finish work

1 3 5 7 9
Month
Project Network

• Activity-on-node (AON)
– nodes represent activities,
and arrows show
precedence relationships
• Event Node
– completion or beginning
of an activity in a project
1 2 3

Branch
AON Network for House Building Project

Lay foundations Build house

2 4
Finish work
2 3
7
Start 1 1
3
Design house 6
and obtain
3
1 5 1
financing
1 Select carpet
Order and receive
materials Select paint
Critical Path

2 4
2 3
7
Start 1 1
3

3 6
1 5 1
1

A: 1-2-4-7  Critical path


3 + 2 + 3 + 1 = 9 months
B: 1-2-5-6-7  Longest path
3 + 2 + 1 + 1 + 1 = 8 months through a network
C: 1-3-4-7  Minimum project
3 + 1 + 3 + 1 = 8 months
completion time
D: 1-3-5-6-7
3 + 1 + 1 + 1 + 1 = 7 months
Activity Start Times

Start at 5 months

2 4
Finish at 9 months
2 3
7 Finish
Start 1 1
3

3 6
1 5 1
1 Start at 6 months
Start at 3 months
Node Configuration

Activity number Earliest start

Earliest finish
1 0 3

3 0 3 Latest finish

Activity duration Latest start


Activity Scheduling
• Earliest start time (ES)
– earliest time an activity can start
– ES = maximum EF of immediate predecessors
• Forward pass
– starts at beginning of CPM/PERT network to determine earliest
activity times
• Earliest finish time (EF)
– earliest time an activity can finish
– earliest start time plus activity time
– EF= ES + t
Earliest Activity Start and Finish Times

Lay foundations
Build house
2 3 5
Start 4 5 8
2
3

1 0 3 7 8 9
3 1
Design house
and obtain 6 6 7 Finish work
financing 3 3 4
1
1 5 5 6
Select carpet
Order and receive 1
materials Select pain
Activity Scheduling (cont.)
• Latest start time (LS)
– Latest time an activity can start without delaying critical path
time
– LS= LF - t
• Latest finish time (LF)
– latest time an activity can be completed without delaying critical
path time
– LF = minimum LS of immediate predecessors
• Backward pass
– Determines latest activity times by starting at the end of
CPM/PERT network and working forward
Latest Activity Start and Finish Times

Lay foundations
Build house
2 3 5
Start 4 5 8
2 3 5
3 5 8

1 0 3 7 8 9
3 0 3 1 8 9
Design house
and obtain 6 6 7 Finish work
financing 3 3 4
1 7 8
1 4 5 5 5 6
Select carpet
Order and receive 1 6 7
materials Select pain
Activity Slack
ES = LS or EF = LF indicates critical path

ES-LS or EF-LF indicates slack time

Activity LS ES LF EF Slack S
*1 0 0 3 3 0
*2 3 3 5 5 0
3 4 3 5 4 1
*4 5 5 8 8 0
5 6 5 7 6 1
6 7 6 8 7 1
*7 8 8 9 9 0
* Critical Path
Slack Time and Critical Path(s)

• Slack is the length of time an activity can


be delayed without delaying the project
Slack = LS – ES

• Activities with 0 slack are Critical Activities


• The Critical Path is a continuous path
through the network from start to finish that
include only critical activities
Total Slack Time vs. Free Slack Time

• Total slack time is shared by more than 1


activity

• Free slack time is associated with only 1


activity
Activity Slack
Total Slack Time is shared by activity 3-5-6.

What is the implication of this situation?

Activity LS ES LF EF Slack S
*1 0 0 3 3 0
*2 3 3 5 5 0
3 4 3 5 4 1
*4 5 5 8 8 0
5 6 5 7 6 1
6 7 6 8 7 1
*7 8 8 9 9 0
* Critical Path
Latest Activity Start and Finish Times
Activity 3-5-6 together can
be delayed by 2 months and
not by 3 months.
Lay foundations
Build house
2 3 5
Start 4 5 8
2 3 5
3 5 8

1 0 3 7 8 9
1 0 3 1 8 9
Design house
and obtain 6 6 7 Finish work
financing 3 3 4
1 7 8
1 4 5 5 5 6
Select carpet
Order and receive 1 6 7
materials Select pain
EXERCISE # 1

Data
Precedence
Activity Time Relationships
A 3
B 5
C 7 A
D 5 A
E 4 B,C
F 6 B
G 2 E,D
H 3 F
1. Develop a Gantt chart
2. Determine the total project completion time and critical path.
Network Diagram

A D
G

End
Start C

E H
B

Critical path = A-C-E-G


Project length = 16 weeks
Analysis

Activity Time ES EF LS LF Slack Critical?


A 3 0 3 0 3 0 Y
B 5 0 5 2 7 2 N
C 7 3 10 3 10 0 Y
D 5 3 8 9 14 6 N
E 4 10 14 10 14 0 Y
F 6 5 11 7 13 2 N
G 2 14 16 14 16 0 Y
H 3 11 14 13 16 2 N

Critical path = A-C-E-G


Project length = 16 weeks
Exercise # 2

Data
Precedence
Activity Time Relationships
A 2
B 5
C 1
D 10 B
E 3 A,D
F 6 C
G 8 E,F

1. Develop a Gantt chart


2. Determine the total project completion time and critical path.
Network Diagram

B D

E
Start

A G

F
C
Analysis

Activity Time ES EF LS LF Slack Critical?


A 2 0 2 13 15 13 N
B 5 0 5 0 5 0 Y
C 1 0 1 11 12 11 N
D 10 5 15 5 15 0 Y
E 3 15 18 15 18 0 Y
F 6 1 7 12 18 11 N
G 8 18 26 18 26 0 Y

Critical path = B-D-E-G


Project length = 26 days
Exercise # 3

Data
Activity Time Precedence Relationships
1 4
2 7
3 8 1
4 3 1
5 9 2
6 5 3
7 2 3
8 6 4 5 6
9 5 2
Gantt Chart
Gantt Chart

7
Activity

0 5 10 15 20 25

Time
Project Scheduling
Schedule
Early Early Late Late
Activity Start Finish Start Finish Slack
1 0 4 0 4 0
2 0 7 1 8 1
3 4 12 4 12 0
4 4 7 14 17 10
5 7 16 8 17 1
6 12 17 12 17 0
7 12 14 21 23 9
8 17 23 17 23 0
9 7 12 18 23 11
Duration 23

You might also like