Oil & Gas Processing Plants

Design and Operation


COMMISSIONING Training Course

DGEP/SCR/ED/ECP - 7/18 October 2002


COMMISSIONNING OF OIL AND GAS
PROCESSING PLANTS

DGEP/SCR/ED/ECP - 7/18 October 2002


COMMISSIONNING OF OIL AND GAS PROCESSING PLANTS : CONTENTS

• 1- COMPLETION ACTIVITIES DEFINITION

• 2- DESCRIPTION OF THE METHODOLOGY

• 3- OVERALL SEQUENCE AND DOSSIERS OF COMPLETION ACTIVITIES

• 4 - TOOLS (ICAPS)

• 5 - CONTRACTUAL ASPECT AND ORGANIZATION

• 6- TFE PRECOMMISSIONING AND COMMISSIONING POLICY

• 7- CONCLUSION : EXPERIENCE OF TFE

• 8- QUESTION / ANSWER SESSION

DGEP/SCR/ED/ECP - 7/18 October 2002 3


COMPLETION ACTIVITIES DEFINITION

1 - COMPLETION ACTIVITIES DEFINITION

DGEP/SCR/ED/ECP - 7/18 October 2002 4


Project phase and completion activities

Operations

Routine operation
Provisional
Acceptance
START-UP
Ready for
COMMISSIONING StartUp
EXECUTION Mechanical
PRECOMMISSIONING Completion
EXECUTION
Commissioning preparation
CONSTRUCTION
PROJECT

&
COMPLETION ACTIVITIES DEFINITION

Precommissioning preparation
PROCUREMENT

5
DETAILED

General preparation
ENGINEERING
BASIC
ENGINEERING

DGEP/SCR/ED/ECP - 7/18 October 2002


Pre-Project
Preliminary and
conceptual studies
COMPLETION ACTIVITIES DEFINITION

COMPLETION ACTIVITIES = PRECOMMISSIONING + COMMISSIONING

- Verifications just before the Plant is brought on line to ensure that every
piece of equipment operates as per design.

- Ultimate goals : make the plant oil or gas in as safe and troublefree as
possible.

- Rough split :
¤ Precommissioning = Static Tests
¤ Commissioing = Dynamic Tests

START - UP

DGEP/SCR/ED/ECP - 7/18 October 2002 6


COMPLETION ACTIVITIES DEFINITION

PHASE ACTIVITIES MILESTONE

CONFORMITY CHECKS
PRECOMMISSIONING MECHANICAL
STATIC TESTING COMPLETION
FLUSHING & CLEANING

ENERGIZATION

DYNAMIC TESTS READY FOR


COMMISSIONING START - UP
EQUIPMENT RUNNING-IN

PRESTART-UP ACTIVITIES

OIL & GAS IN


PROVISIONAL
START - UP BRINGING PLANT ON LINE ACCEPTANCE
PERFORMANCE TESTS

DGEP/SCR/ED/ECP - 7/18 October 2002 7


COMPLETION ACTIVITIES DEFINITION

¤ PRECOMMISSIONING :
- Visual inspection of equipment ( PG , motors , cables...).
Quality of installation
Compliance with Project specs , safety rules, codes,...

- « Cold testing » : calibration of instruments, machinery alignement ,


setting of safety valves ,pressure testing of piping...(De-energised tests)
- Pipes and vessels air or water flushing and cleaning
¤ COMMISSIONING :
- Electrical motors uncoupled runs , instrument loops test , electrical
breakers operation .......
- Running-in and on-line tests of plant utilities, and main process
equipment in closed loop (wherever applicable)
-Piping drying out , leak testing , inerting or loading of various
chemicals
DGEP/SCR/ED/ECP - 7/18 October 2002 8
COMPLETION ACTIVITIES DEFINITION

COMMISSIONING

ALL THE TEST ACTIVITIES


CARRIED - OUT ON A NEW PLANT
BETWEEN
THE END OF CONSTRUCTION
AND
THE PRODUCTION START -UP

DGEP/SCR/ED/ECP - 7/18 October 2002 9


DESCRIPTION OF THE METHODOLOGY

2 - DESCRIPTION OF THE METHODOLOGY

2 - 1 The « System approach »


2 - 2 Precommissioning methodology
2 - 3 Commissioning methodology

DGEP/SCR/ED/ECP - 7/18 October 2002 10


DESCRIPTION OF THE METHODOLOGY : system approach

2-1 The « System approach »

DGEP/SCR/ED/ECP - 7/18 October 2002 11


DESCRIPTION OF THE METHODOLOGY : system approach

« SYSTEM APPROACH »

- CONSTRUCTION : By Trades and Areas


( Not all parts of the Plant reach the same degree of completion at
the same time )
- START-UP SEQUENCE : Driven by Operational Constraints
( completion of multi-trade operational units : Fire water , pump ,
power generation...etc )

Optimization of Completion Activities & Start-up by « SYSTEM»


« Subdivision of an Installation that performs a given operational
function with no or little interference from the other parts of the Plant »

DGEP/SCR/ED/ECP - 7/18 October 2002 12


DESCRIPTION OF THE METHODOLOGY : system approach

Projet without system approach

Project

Projet with system approach

Sous-systeme 1 TIME BENEFIT


Sous-systeme 2

Sous-systeme 3

Pre-Comm Comm Start-Up

DGEP/SCR/ED/ECP - 7/18 October 2002 13


DESCRIPTION OF THE METHODOLOGY : system approach

Sub-system break-down

Fuel Utility
Oil Gas Water

Exch
Oil to
A Utilities

Exch
B

Exch
C
Heat A Heat B

Drain

DGEP/SCR/ED/ECP - 7/18 October 2002 14


DESCRIPTION OF THE METHODOLOGY : system approach

Sub-system and discipline

VESSELS & PIPING


INSTRUMENTS

ELECTRICAL

MECHANICAL PUMP MOTOR

DGEP/SCR/ED/ECP - 7/18 October 2002 15


DESCRIPTION OF THE METHODOLOGY : precommissioning

2-2 Precommissioning methodology

DGEP/SCR/ED/ECP - 7/18 October 2002 16


DESCRIPTION OF THE METHODOLOGY : precommissioning

PRECOMMISSIONING METHODOLOGY

TASK DISCIPLINE NUMBER SUPPORT DOCUMENT

- 1 per item of - 1 Check List per type of


equipment ( Field ) equipment & subsystem(Field)
Conformity Checks All
- 1 Check List per package
- 1 per package
- 1 List of checks in the
Status Index

- 1 test per specified - 1 Test Sheet per test


Static Tests All item ( Field )
- 1 test per safety - List of tests in the
item ( Package ) Status Index

Flushing & Cleaning Process - 1 per subsystem or - Specific procedure &


Network or TestPack report

DGEP/SCR/ED/ECP - 7/18 October 2002 17


DESCRIPTION OF THE METHODOLOGY : commissioning

2-3 Commissioning methodology

DGEP/SCR/ED/ECP - 7/18 October 2002 18


DESCRIPTION OF THE METHODOLOGY : commissioning

COMMISSIONING METHODOLOGY

TASK DISCIPLINE NUMBER SUPPORT DOCUMENT

Preliminary Checks All - 1 per subsystem - 1 task report form per


subsystem + punch list
items in Precomm.
- 1 per package dossier

Electrical - 1 test per Basic - 1 Functional Test Sheet


Functional Tests Instruments Function List of tests in
Telecommunication Technical Data Base

- 1 operational Test
Operational Tests Test:multi-discipline - 1 per subsystem or Procedure by
Network Subsystem, specific
to the installation

- 1 per subsystem,or - Leak test, Inerting...


Pre-Start up Activities Process level of pressure, or reports, specific to the
main circuit Installation

DGEP/SCR/ED/ECP - 7/18 October 2002 19


DESCRIPTION OF THE METHODOLOGY : commissioning

Basic Function

- Item or group of items of equipment that performs


an elementary function of the plant

- It is the smallest equipment which can be subject


to a Commissioning operation

- e.g : Switchboards , transformers, heaters, process


control loops , loudspeaker loops , pumps , vessels ,
etc , ....

DGEP/SCR/ED/ECP - 7/18 October 2002 20


DESCRIPTION OF THE METHODOLOGY : Sequence & dossiers

3 - Overall sequence and dossiers of Completion Activities

DGEP/SCR/ED/ECP - 7/18 October 2002 21


DESCRIPTION OF THE METHODOLOGY : Sequence & dossiers

HANDOVER PROCEDURE

by sub-system by sub-system by sub-system


or functional system

READY FOR OPERATIONAL READY FOR PLANT PROVISIONAL FINAL


cc
COMMISSIONING HAND OVER
TEST START UP ACCEPTANCE ACCEPTANCE
CERTIFICATE TT
CERTIFICATE CERTIFICATE STATE CERTIFICATE CERTIFICATE
MAIN ACTIVITY

CONSTRUCTION PLANT - IN
GAS - IN
OPERATION
COMMISSIONING

PERFORMANCE
START-UP ROUTINE OPERATIONS
TEST
MECHANICAL
COMPLETION (ALL UTILITIES PROCESS
SUBSYSTEMS)
READY FOR START
UP
DETAILED ACTIVITY (ALL SUBSYSTEMS)
Construction and precommissioning
Functional testing

Operational tests Post Gas-In Performance Warranty period


OPERATIONAL OTs Test
Pre Start-up activities
RESPONSABILITY
CONTRACTOR CONSTRUCTION

CONTRACTOR COMMISSIONING

COMPANY OPERATIONS

CONTRACTOR COMPANY

Permit to Work
Responsibility

DGEP/SCR/ED/ECP - 7/18 October 2002 22


DESCRIPTION OF THE METHODOLOGY : Sequence & dossiers

Precommissioning dossier
Combined RFC Certificate

One Dossier
Per Sub-
System

DGEP/SCR/ED/ECP - 7/18 October 2002 23


DESCRIPTION OF THE METHODOLOGY : Sequence & dossiers

Commissioning dossier

RFSU Dossier Index RFSU Certificate

One Dossier Per


Sub-System

DGEP/SCR/ED/ECP - 7/18 October 2002 24


DESCRIPTION OF THE METHODOLOGY : Sequence & dossiers

Hand-over dossier
RFHO
Certificate
SUB SYSTEM
XX
SUB SYSTEM
YY
SUB SYSTEM

One Dossier
Per Hand Over
ZZ

Unit

DGEP/SCR/ED/ECP - 7/18 October 2002 25


DESCRIPTION OF THE METHODOLOGY : Sequence & dossiers

Overall dossiers

308m 273m 206 HOU Dossiers


849 RFSU Dossiers
891 RFC Dossiers
1,946 Dossiers

DGEP/SCR/ED/ECP - 7/18 October 2002 26


DESCRIPTION OF THE METHODOLOGY : tools

4 - Tools ( ICAPS )

DGEP/SCR/ED/ECP - 7/18 October 2002 27


DESCRIPTION OF THE METHODOLOGY : tools

DGEP/SCR/ED/ECP - 7/18 October 2002 28


DESCRIPTION OF THE METHODOLOGY : tools

EXECUTION
PREPARATION PUNCH LIST

OPERCOM

FORMS PROGRESS

POPULATION

ENGINEERING REPORTING

DGEP/SCR/ED/ECP - 7/18 October 2002 29


DESCRIPTION OF THE METHODOLOGY : organization and contract

5 - Contractual aspects and organization

DGEP/SCR/ED/ECP - 7/18 October 2002 30


DESCRIPTION OF THE METHODOLOGY : organization and contract

contractual aspects
- The Organization depends on the chosen strategy for the project and its
associated contractual schemes :
- E , P , C = separate contracts
- EPC = single contract
- EPCC + SU ( Turnkey )
- Responsability of completion activities ,
- Precommissioning by Contractors always
- Commissioning by Company if E , P , C or EPC
- Commissioning by Contractor if EPCC or turnkey

Commissioning methodology set up without presupposing which party is


in charge
It is the contract that stipulates « who does what » exactly

DGEP/SCR/ED/ECP - 7/18 October 2002 31


DESCRIPTION OF THE METHODOLOGY : organization and contract

Transfer of responsability
- Generally :
- Contractors
- Company ( Project team )
- Company ( Operation team )
- Depending on contracts these transfers happen at various stages :

Contract Contractor / Company Project / Operations


EPC RFC RFHO
EPCC RFHO RFSU

- Transfer for Operation , Maintenance and Safety


(The accepting party is responsible for the consequences resulting from
misoperation )
- But Engineering / Construction contractors or vendors are not relieved
from their contractual obligations

DGEP/SCR/ED/ECP - 7/18 October 2002 32


DESCRIPTION OF THE METHODOLOGY : organization and contract

General chart

TYPE A Project Manager (a) (a) or surface Manager in integrated project organisation

Construction (b) Operations

(b) including precommissioning activity Commissioning

TYPE B Project Manager

Construction (b) Commissioning

(b) including precommissioning activity

TYPE C Project Manager Operations

Construction (b) Commissioning

(b) including precommissioning activity

DGEP/SCR/ED/ECP - 7/18 October 2002 33


DESCRIPTION OF THE METHODOLOGY : organization and contract

Commissioning
chart

DGEP/SCR/ED/ECP - 7/18 October 2002 34


DESCRIPTION OF THE METHODOLOGY : TFE P/C and Com policy

6 - TFE precommissioning and commissioning policy

DGEP/SCR/ED/ECP - 7/18 October 2002 35


DESCRIPTION OF THE METHODOLOGY : TFE P/C and Com policy

TFE precommissioning and commissioning


policy is defined in a common PJC/EXP
Company Rules :
CR PJC 311

DGEP/SCR/ED/ECP - 7/18 October 2002 36


DESCRIPTION OF THE METHODOLOGY : TFE P/C and Com policy

Rule #1
OPERCOM methodology as defined in GS EXP 101,103,105,107 is
mandatory
Rule#2
ICAPS is the mandatory software to be used
Rule#3
Precommissionning is Contractor’s responsibility
Rule#4
Field operation personnel has to witness commissionning activities
Rule #5
For each subsystem, an appropriate Interim Certificate must be issued for
RFC and RFSU
Rule #6
Hand Over Certificates must be issued at the formal transfers of
responsabilities.
Rule #7
The Commissioning Team must be at least at the same reporting level as
the Construction Team within the Project Organisation.

DGEP/SCR/ED/ECP - 7/18 October 2002 37


DESCRIPTION OF THE METHODOLOGY : TFE P/C and Com policy

Recommandation #1
Commissionning activities should be the responsability of the Contractor :
i.e EPSCC or EPSCIC Contracts shoud be the preferred case. Selection of
the contractual strategy will be part of the first issue of the Project Execution
Plan (PEP) and will be validated by TDO/PJC and EXP at CTP n° 1.
Recommandation #2
A standard organisation as defined herebelow in article 4.3 should be set
up for commissionning activities.

DGEP/SCR/ED/ECP - 7/18 October 2002 38


DESCRIPTION OF THE METHODOLOGY : TFE experience

7 - CONCLUSION : Experience of TFE

DGEP/SCR/ED/ECP - 7/18 October 2002 39


DESCRIPTION OF THE METHODOLOGY : TFE experience

COST : 3 to 5% of the cost of the Project

DURATION : 4 to 8 Months of Preparation


4 to 8 Months of Execution
MANHOURS : 30,000 to 200,000 Manhours of execution
10% of the construction Manhours
HISTOGRAM : 40 to 200 persons of execution ( Peak ).

DGEP/SCR/ED/ECP - 7/18 October 2002 40