You are on page 1of 28

4.2.

19
Performing Pressure Tests on Gas
Distribution Lines

Gas personnel must understand how to perform pressure


tests on gas distribution lines to ensure the system is gas
tight.

In this module you will learn to identify:


(1) NFPA 54 regulations that apply to pressure testing of a
propane distribution system
(2) Basic elements of pressure testing
(3) Procedures commonly used to pressure test propane piping

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 1
NFPA 54 Regulations that Apply to Pressure Testing
NFPA 54 7.1.4.1 Test pressure shall be measured with a manometer or with a
pressure measuring device designed and calibrated to read, record,
2002 or indicate a pressure loss due to leakage during the pressure test
period. The source of pressure shall be isolated before the pressure
tests are made. Mechanical gauges used to measure test pressures
shall have a range such that the highest end of the scale is not
greater than 5 times the test pressure.
7.1.4.2 The test pressure to be used shall be no less than 1-½ times the proposed
maximum working pressure, but not less than 3 psi, irrespective of design pressure.

7.1.4.3 Test duration shall be not less than ½ hour for each 500 cubic feet of pipe
volume or fraction thereof. When testing a system having a volume less than 10
cubic feet or a system in a single-family dwelling, the test duration shall be a
minimum of 10 minutes. The duration of the test shall not be required to exceed 24
hours.

4.2.19 Student Book  © 2004 Propane Education & Research Council


NFPA 54 Regulations that Apply to Pressure Testing
NFPA 54 7.1.1.3 Where repairs or additions are made following the pressure
test, the affected piping shall be tested. Minor repairs and additions
2002 are not required to be pressure tested provided that the work is
inspected and connections are tested with a non-corrosive leak-
detecting fluid or other leak-detecting methods approved by the
authority having jurisdiction.
7.1.1.4 Where new branches are installed from the point of delivery to new
appliance(s), only the newly installed branch(es) shall be required to be pressure
tested. Connections between the new piping and the existing piping shall be tested
with a non-corrosive leak-detecting fluid or approved leak-detecting methods.

7.1.1.5 A piping system shall be tested as a complete unit or in sections. Under no


circumstances shall a valve in a line be used as a bulkhead between gas in one
section of the piping system and test medium in an adjacent section, unless two
valves are installed in series with a valved “tell tale” located between these valves.
A valve shall not be subjected to the test pressure unless it can be determined that
the valve, including the valve closing mechanism, is designed to safely withstand
the pressure.

4.2.19 Student Book  © 2004 Propane Education & Research Council Pages 1 & 2
Identifying Basic Elements of Pressure Testing
Test Medium. According to NFPA 54, 7.1.2, the test medium shall be air,
nitrogen, or carbon dioxide, or an inert gas. Do not use oxygen or fuel gas.

Test Pressure. NFPA 54 requires a test pressure that is 1 ½ times the


maximum working pressure for the piping section, but not less than 3 psig.
For example, pipe supplying propane vapor to a second-stage or 2-PSI service
regulator may have a working pressure of 10 psig. In this situation, the test
pressure is at least 15 psig (1 ½ x 10). However, the second stage pipe supplying
propane to the appliances has an operating pressure of 11 inches water column.
In this situation, the test pressure is at least 3 psig, and appliances and their
controls are not connected to the piping system during the test.

Test Duration NFPA 54 and most state and local codes require a 10 minute
test duration for single-family dwellings and small capacity distribution systems
with less than 10 cubic feet (1,840 lineal feet of 1” steel pipe). However, if the
distribution piping is more than 10 cubic feet, NFPA 54, requires a test duration of
30 minutes for each 500 cubic feet of piping. Regardless of size, NFPA 54 states
that the duration of the test need not exceed 24 hours.

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 2
NFPA 54 Regulations that Apply to Pressure Testing
Pressure Measuring Devices. NFPA 54,
7.1.4.1 requires: Test pressure shall be measured
with a pressure measuring device designed and
calibrated to read, record, or indicate a pressure
loss due to leakage during the pressure test period.
The source of pressure shall be isolated before the
pressure tests are made.
Mechanical gauges used to measure test
pressures shall have a range such that the highest Figure 1. Test Gauges Installed
end of the scale is not greater than 5 times the test At Piping Connections at Two
pressure. 2-PSI Piping Service Entrances

For example, a 0-15 psi gauge should be used for


a 3 psig pressure test, while a 0-75 psi gauge is
required for a 15 psig test.

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 3
Procedures Used to Pressure Test Propane Piping

Before testing, check the installation carefully to be sure it is properly


installed and meets applicable state and local codes and regulations.
• All pipe, tubing, and fittings used in the installation must meet the requirements
in all applicable state and local codes and standards, particularly the National
Fuel Gas Code, NFPA 54.
• For new installations, the underground lines and the lines inside buildings must
be left uncovered for the duration of the pressure testing.
• All aboveground lines must be properly supported as necessary, and protected
from physical damage.
• Before beginning a test, be sure the gauge(s) and test fittings are in good
condition. Test fittings equipped with Schrader valves should be fitted with
appropriate sealing caps and cap gaskets.

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 4
Procedures Used to Pressure Test Propane Piping
Pressure Testing Integral Two-Stage Distribution Systems: 11 Inches
Water Column Operating Pressure— Integral 2-Stage Regulator
Pressure
Minimum Test Measuring
Description Test Pressure Test Medium
Duration Device
Before A pressure gauge
appliances are 3 psig minimum 10 minutes Air, nitrogen, or designed and
connected carbon dioxide calibrated to read,
record, or indicate
a pressure loss
due to leakage
during the
pressure test
period.
Figure 2. Pressure Testing Integral Two-Stage Distribution
Lines Operating Pressure: 11 Inches Water Column
This method is intended for testing the main and branch lines before they are connected
to the appliance shutoff valves and the integral two-stage regulator. The piping system
must withstand a test pressure of at least 3 psig for a minimum of 10 minutes without
showing any drop in pressure.

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 4
Procedures Used to Pressure Test Propane Piping

Figure 3. Example of Integral Two-Stage Piping Diagram

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 5
Procedures Used to Pressure Test Propane Piping

Step 1: Make sure the entire line is disconnected from the propane
storage container regulator and the ends of all branch lines
are either capped or plugged.

Step 2: Install a test adaptor and suitable gauge at any connection


in the piping system.

Step 3: Install in the piping system a pressure-measuring device


designed and calibrated to read, record, or indicate a
pressure loss caused by leakage.

Step 4: Pressurize the piping system to at least 3 psig. A hand


pump may be used, as illustrated in Figure 4. The source
of pressure shall be isolated before the pressure test is
made.

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 5
Procedures Used to Pressure Test Propane Piping

Step 5: Ensure the pressure on the piping system being pressure


tested remains constant for a minimum time period of 10
minutes.

Step 6: If the piping system holds the test pressure for a minimum
of 10 minutes without any drop, the piping system is
considered gastight. (If the piping system is not
considered gastight, take appropriate action to locate the
leak and make necessary repairs.)
Step 7: Prepare a record that indicates which portions of the piping
system were pressure-tested.

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 5
Procedures Used to Pressure Test Propane Piping
Pressure Testing Two-Stage Distribution Systems: 11 Inches Water
Column Final Delivery Pressure— 1st & 2nd Stage Regulators
Pressure
Minimum Test Measuring
Description Test Pressure Test Medium
Duration Device
Buried Not less than 1.5
Distribution Line (1½) times the 10 minutes Air, nitrogen, or
A pressure gauge
(before regulator maximum working carbon dioxide
pressure of the first designed and
is installed). stage line. The calibrated to
typical working read, record, or
pressure of the first indicate a
stage regulator is pressure loss due
10 psig; therefore,
the test pressure
to leakage during
should be at least the pressure test
15 psig. period.
Second Stage
Line, Before 3 psig minimum 10 minutes Air, nitrogen, or
appliances are carbon dioxide
installed.
Figure 5. Pressure Testing Two Stage Distribution Lines
Appliance Operating Pressure: 11" w.c.
4.2.19 Student Book  © 2004 Propane Education & Research Council Page 6
Procedures Used to Pressure Test Propane Piping

Figure 6. Pressure Testing First-Stage Line

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 7
Procedures Used to Pressure Test Propane Piping

Step 1: Disconnect the line from the storage container regulator


and the second-stage regulator.

Step 2: Plug or cap the terminating ends of the first-stage line.

Step 3: Install a pressure-measuring device designed and


calibrated to read, record, or indicate a pressure loss due
to leakage during the pressure test period in the container
end of the line.

Figure 7. Installing Test Gauge and Fittings

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 7
Procedures Used to Pressure Test Propane Piping

Step 4: Pressurize the piping system to at least 15 psig. (An air


pump may be used, as illustrated in Figure 6.) Then
isolate the source of pressure.
Step 5: Ensure the pressure remains constant for a minimum time
period of 10 minutes.
Step 6: If the line holds the test pressure without any drop, the line
is considered gastight. (If the line is not considered
gastight, take appropriate action to locate the leak and
make necessary repairs.)

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 8
Procedures Used to Pressure Test Propane Piping

Step 7: Prepare a record indicating the section(s) of pipe tested.

Figure 8. Recording the Pressure Test

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 8
Procedures Used to Pressure Test Propane Piping
Test the second-stage line(s) by using the same basic method used for
integral two-stage systems (a minimum 3-psig test for 10 minutes).
Fr
s
it
S t
age
Regua lt
or
Pessur
r e
Gauge
H
andP
ump

S
er
viceV
alve Pp
i eC
ap Pp
i eC
ap
AC
r
i heckor
N
eedleV alve
S
t
orage
C
ontainer

Pp
i eC
ap

Disconnect ed
2ndS t
age
R egulator
Figure 9. Pressure Testing Distribution Lines
Downstream of 2nd-Stage Regulator

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 9
Procedures Used to Pressure Test Propane Piping
Pressure Testing 2-Pound Distribution Systems: 10 psig buried distribution line
pressure and 2-psi delivery pressure to one or more line regulators controlling 11
inches water column final delivery pressure. If the system uses a first-stage and
2-PSI service regulators connected by a buried distribution line, the system is tested as
a two-stage piping system (Figure 10).
Fir st- Stage
Regulao tr
( 10psigoutletpressure)

Bur iedPETubing

Water Heater
2- psiSer vice
Regulaotr Fur nace
(2 p s ig o u tle tp re s s u re ) Dr yer
R
LineRegulator Manifold

Figure 10. Range

2-Pound (Hybrid) Pressure System


4.2.19 Student Book  © 2004 Propane Education & Research Council Page 9
Procedures Used to Pressure Test Propane Piping
Pressure
Minimum Test Measuring
Description Test Pressure Test Medium
Duration Device
Buried Not less than 1.5
Distribution Line (1½) times the 10 minutes Air, nitrogen, or
A pressure gauge
(before regulator maximum working carbon dioxide
pressure of the first designed and
is installed). stage line. The calibrated to
typical working read, record, or
pressure of the first indicate a
stage regulator is 10 pressure loss due
psig; therefore, the
test pressure should
to leakage during
be at least 15 psig. the pressure test
period.
Line Connecting
2-PSI Service 3 psig minimum 10 minutes Air, nitrogen, or
Regulator to carbon dioxide
Distribution
Manifold.
Distribution Man-
fold and 3 psig minimum 10 minutes Air, nitrogen, or
distribution lines carbon dioxide
to appliances

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 10
Procedures Used to Pressure Test Propane Piping

AirValve-E quipped
TestFn
ti gw th
i
Fir
st-Stage 0to60psG i auge
R egulator 2-PSIService
Regulator

Pp
ie
C
ap

2psg iC S STLn
i eto
DistributionManifold

P E First-S tage
D
istributionLine
Figure 12. Pressure Testing First-Stage Line

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 11
Procedures Used to Pressure Test Propane Piping

Step 1: Disconnect the line from the storage container regulator


and the second-stage regulator.

Step 2: Plug or cap the terminating ends of the first-stage line.

Step 3: Install a pressure-measuring device designed and


calibrated to read, record, or indicate a pressure loss due
to leakage during the pressure test period in the container
end of the line.

Step 4: Pressurize the piping system to at least 15 psig. Then


isolate the source of pressure.

Step 5: Ensure the pressure remains constant for a minimum time


period of 10 minutes.

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 11
Procedures Used to Pressure Test Propane Piping

Step 6: If the line holds the test pressure without any drop, the line
is considered gastight. (If the line is not considered
gastight, take appropriate action to locate the leak and
make necessary repairs. Repeat the pressure test as
needed until a gastight condition is maintained.)
Step 7: Prepare a record indicating the section(s) of pipe tested.

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 11
Procedures Used to Pressure Test Propane Piping
To test lines in a 2-psi system that uses a single line regulator and
distribution manifold:
Step 1: Remove the line regulator located upstream of the distribution
manifold and replace with a pipe nipple. (Figure 13) Verify
that all valves at the manifold are manufacturer approved for
the pressure that will be used for the test and that the valves
are in their open positions.

Figure 13a. Line Regulator Figure 13b. Line Regulator


and Manifold Replaced with Pipe Nipple
for Pressure Test
4.2.19 Student Book  © 2004 Propane Education & Research Council Page 11
Procedures Used to Pressure Test Propane Piping

Step 2: Plug or cap the terminating ends of the lines at appliance


locations.

Step 3: Install a pressure-measuring device designed and calibrated


to read, record, or indicate a pressure loss due to leakage
during the pressure test period in the outside connection
where the 2-PSI service regulator is disconnected for the
pressure test.
Step 4: Pressurize the piping system to at least 3 psig. Then isolate
the source of pressure.

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 12
Procedures Used to Pressure Test Propane Piping

Step 5: Ensure the pressure remains constant for a minimum time


period of 10 minutes.

Step 6: If the line holds the test pressure without any drop, the lines
and manifold are considered gastight. (If the lines are not
considered gastight, take appropriate action to locate the leak
and make necessary repairs. Repeat the pressure test as
needed until a gastight condition is maintained.)
Step 7: Prepare a record indicating the section(s) of pipe tested.

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 12
Procedures Used to Pressure Test Propane Piping

W
at
erH
eat
er
2-psiService
Regulat
or
Furnace
D
ryer
R M
anif
old
Ln
ie
Regulat
or
R
P
last
icP
p
i einS
lab R
ange

CSSTHyb
ridDu
al Pre
ssu
reSyste
m

Figure 14. 2-PSI System


with 2 Line Regulators

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 13
Procedures Used to Pressure Test Propane Piping

Fur nace Water Heater


80,000Btuh 36,000Btuh

2- psiSer vice
Regulaotr
Line Dr yer
Regulao
tr 28,000Btuh
R
A=20feet Manifold Range
52,000Btuh
B=40feet
Fur
60,0nace
00Btuh

WaterH
0eat
36, 00e
Brtuh
R
Manifold
Line
Regulao
tr
Fir eplace
45,000Btuh

CS15.
Figure ST 2-PSI Mul ti
CSST pl e Mani fol d System
Multiple
Manifold System

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 13
Procedures Used to Pressure Test Propane Piping

Be sure to comply with your company’s pressure testing


procedures, along with code requirements of jurisdictional
authorities in your area. Also read and follow manufacturer
recommendations for pressure testing corrugated stainless
steel tubing as appropriate.

4.2.19 Student Book  © 2004 Propane Education & Research Council Page 13
Time to See If You Got the Key Points of
This Module…
• Complete the Review on page 14.

• See if you are ready for the Certification


Exam by checking off the
performance criteria on page 15.

4.2.19 Student Book  © 2004 Propane Education & Research Council Pages 14 & 15

You might also like