Professional Documents
Culture Documents
[source: moneyhero.com.hk]
Mutually exclusive alternatives
Considerations:
Investments
Revenues
Costs
Useful life of project
What criterion is used for comparison
A common practice is:
- Set the choice with the minimum initial investment
with acceptable IRR as base alternative
- For each of the remaining, check if additional
investment is justifiable
Role of MARR in comparisons
A B
60000 73000
• If MARR=10%:
• PWA=−60000+22000(P/A,10%,4)=9,738: Base Alternative
• PWB=−73000+26225(P/A,10%,4)=10,131: PWB is preferred
• If MARR=15%:
• PWA=−60000+22000(P/A,15%,4)=2,809: Base Alternative
• PWB=−73000+26225(P/A,15%,4)=1,872: PWB is NOT preferred
• If MARR=11.39%:
• PWA=−60000+22000(P/A,11.39%,4)=7,689: Base Alternative
• PWB=−73000+26225(P/A,11.39%,4)=7,689: PWB is the same as Base
Identical useful lives: example
Alternative A Alternative B
Capital investment 60,000 73,000
Annual revenue 22,000 26,225
IRR 17.30% 16.26%
PW (MARR) 9738 10131
@ IRR @ MARR
Notice that the IRR method any (net) income is re-invested @ 17.3%
but the PW method any (net) income is reinvested @ MARR (=10%)
More on IRR
You can verify that alternative E will have the highest PW @10%
Comments on the Incremental IRR method
A B C D E F
Investment 900 1500 2500 4000 5000 7000
Annual Income 150 276 400 925 1125 1425
Incremental investment 600 1600 3100 4100 6100
Incremental income 126 250 775 975 1275
Incremental IRR 16.4 9.1 21.4 19.9 16.3
- It is conservative (in terms of spending): invest only if you can earn more
Other methods:
- Cost only comparison:
For each alternative, find the IRR relative to the base investment (i.e. using
incremental return approach) by considering only the investment costs,
operational costs, and salvage value
Comparing alternatives with different useful lives
Alternative 1:
– You can invest $100 in a project
• MARR=3%
– After one year, you will receive $115
• IRR=15%
• PW=111.65
Alternative 2:
– You can extend Alternative 1 to 2 years and receive $121
• IRR=10%
• PW=114.05
Co-terminated model:
In this case, the study period is specified, and all projects will
be evaluated over this period.
We must account for additional salvage value of any
alternative that has useful life longer than study period.
A B
Capital investment 3500 5000
Annual cash flow 1255 1480
Useful life (years) 4 6
1255
MARR = 10%
4 8 12
3500
1480
MARR = 10%
6 12
5000
Repeated investment method: example
4 6
• AW method
– To calculate AW, based on one life cycle for each alternative is
sufficient [Why?]
AWA=−3500(A/P,10%,4)+1255=151
AWB=−5000(A/P,10%,6)+1480=332 > AWA
Repeated investment method: example (cont.)
4 6
We may also use the IRR method (incremental model) for comparing the
alternatives. Here the base alternative is A [Why?]
225
Incremental
cash flow
1500 4775
A B
Capital investment 3500 5000
Annual cash flow 1255 1480
Useful life (years) 4 6
5000
Co-terminated model: example (cont.)
1480
1255
4 6
3500
5000
• For alternative A
FWA,4= −3500(F/P,10%,4) + 1255(F/A,10%,4)
FWA,6= FWA,4(F/P,10%,2) = 847
• For alternative B
FWB,6= −5000(F/P,10%,6) + 1480(F/A,10%,6) = 2561
Co-terminated model: example (cont.)
1255 A 1480 B
3500 5000
225 1480
IRR for incremental
cash flow:
Incremental cash flow 23% > MARR
1500
Selecting a subset of projects from the alternatives
Considerations:
Method:
Combination B1 B2 C1 C2 D Explanation
1 0 0 0 0 0 Accept none
2 1 0 0 0 0 Accept B1
3 0 1 0 0 0 Accept B2
4 0 1 1 0 0 Accept B2 and C1
5 0 1 0 1 0 Accept B2, C2
6 0 1 1 0 1 Accept B2, C1, D
Time period
Project 0 1 2 3 4 PW (MARR=10%)
B1 -50 20 20 20 20 13.4
B2 -30 12 12 12 12 8.0
C1 -14 4 4 4 4 -1.3
C2 -15 5 5 5 5 0.8
D -10 6 6 6 6 9.0
Time period
Combination 0 1 2 3 4 PW (MARR=10%)
1 0 0 0 0 0 0
2 (B1) -50 20 20 20 20 13.4
3 (B2) -30 12 12 12 12 8.0
4 (B2,C1) -44 16 16 16 16 6.7
5 (B2, C2) -45 17 17 17 17 8.8
6 (B2,C1,D) -54 22 22 22 22 15.7
Constraints:
– Total investment cannot exceed the maximum budget
– Each Xi has to be 0 or 1
n
max X i PWi
i 1
n
s.t. Vi X i V
i 1
X i {0,1}
Combination of projects: problem formulation (cont.)
Exclusive constraint
– Projects i and j are mutually exclusive
we need another constraint: Xi + Xj ≤ 1
(we need such a constraint for each pair of mutually
exclusive projects)
Contingent constraint
– Project i can be selected only if project j is selected
we need another constraint: Xi ≤ Xj
(we need such a constraint for each pair of contingent
projects)
Combination of projects: Example
X C1 X B 2 C1 contingent on B2
X C 2 X B2 C2 contingent on B2
X D X C1 D contingent on C1
50 X B1 30 X B 2 14 X C1 15 X C 2 10 X D 48 max budget
X B1 , X B 2 , X C1 , X C 2 , X D {0,1} binary Xi
Acknowledgements:
1. Most of the lecture notes for this course are adapted from those of Prof Xiangtong Qi
2. Course text: Engineering Economy by Sullivan, Wicks, Koelling