ASSEMBLY OF TRUSS
PROPOSED METHOD OF ASSEMBLING
Total Quantity of site Assembling to be done: 39 x 125+2 x 32.6
Weight of Normal (125m) Truss: 1750 MT
Net period available for Assembling: 24 months
Required rate of Assembling: 2.0 Truss/ Month
Each line will comprise of stacking area of Finished Member, Dedicated Gantry of 80
Ton Capacity, Assembling Bed and other requisites.
Assembling will be carried out in two stages. At First the entire truss of 125 m span
will be assembled in 3 components each weighing around 125 Mt.
In the second stage the three members will be further assembled with Bottom and
Top Cross Girders to Complete the entire Span
The site assembly workshop will be an all weather environmental controlled facility
[i.e. covered] for uninterrupted work
TC6 TC3 TJ2 TC2 TJ1 TC1 TJ1 TC2 TJ2 TC3 TC6
TC5 TJ4 TC4 TJ3 TJ3 TC4 TC5
TJ6 TJ5 TJ4 TJ5 TJ6
D10 D6 D5 D4 D3 D2 D1 D1 D2 D3 D5 D7
D8 D7 D4 D6 D8
V1 D9 D10 V1
D9
Weight of Part-I Wt.(MT) Weight of Part-II Wt.(MT) Weight of Part-III Wt.(MT) Weight of Part-IV Wt.(MT) Weight of Part-V Wt.(MT)
1 Wt. of V1 2.847 1 Wt. of TJ4 9.947 1 Wt. of TJ1 12.377 1 Wt. of TJ4 9.947 1 Wt. of V1 2.847
2 Wt. of BJ6 16.443 2 Wt. of TC4 7.931 2 Wt. of TC1 11.228 2 Wt. of TC4 7.931 2 Wt. of BJ6 16.443
3 Wt. of TJ6 5.837 3 Wt. of TJ3 10.991 3 Wt. of TJ1 12.377 3 Wt. of TJ3 10.991 3 Wt. of TJ6 5.837
4 Wt. of D10 5.392 4 Wt. of TC3 10.089 4 Wt. of D1 2.708 4 Wt. of TC3 10.089 4 Wt. of D10 5.392
5 Wt. of TC6 2.19 5 Wt. of TJ2 12.377 5 Wt. of D2 3.685 5 Wt. of TJ2 12.377 5 Wt. of TC6 2.19
6 Wt. of TJ5 13.761 6 Wt. of D7 3.822 6 Wt. of D1 2.708 6 Wt. of D7 3.822 6 Wt. of TJ5 13.761
7 Wt. of BC5 4.332 7 Wt. of D6 5.264 7 Wt. of D2 3.685 7 Wt. of D6 5.264 7 Wt. of BC5 4.332
8 Wt. of BJ5 12.224 8 Wt. of D5 3.812 8 Wt. of BJ2 16.06 8 Wt. of D5 3.812 8 Wt. of BJ5 12.224
9 Wt. of D9 4.325 9 Wt. of D4 4.17 9 Wt. of BJ1 16.06 9 Wt. of D4 4.17 9 Wt. of D9 4.325
10 Wt. of BJ4 12.224 10 Wt. of BJ2 16.06 10 Wt. of BJ4 12.224
11 Wt. of BC3 9.578 11 Wt. of BC1 13.817 11 Wt. of BC3 9.578
12 Wt. of BJ3 14.562 12 Wt. of BC1 13.817 12 Wt. of BJ3 14.562
Total wt. 67.351 Total wt. 104.767 Total wt. 124.582 Total wt. 104.767 Total wt. 67.351
WEIGHT OFADDITIONAL MEMBER
Weight of Intermediates Wt.(MT) Weight of Intermediates Wt.(MT) Weight of Intermediate Wt.(MT) Weight of Intermediate Wt.(MT)
1 Wt. of TC5 6.217 1 Wt. of TC2 11.193 1 Wt. of TC2 11.193 1 Wt. of TC5 6.217
2 Wt. of D8 5.399 2 Wt. of D3 2.942 2 Wt. of D3 2.942 2 Wt. of D8 5.399 TOTAL WT. (MT) 558.398
3 Wt. of BC4 6.849 3 Wt. of BC2 12.19 3 Wt. of BC2 12.19 3 Wt. of BC4 6.849
Total wt. 18.465 Total wt. 26.325 Total wt. 26.325 Total wt. 18.465
South
Bank
North Bank
Launching Concept Bogibeel Bridge
Launching Segment 1
Launching Completed
•For central portion i.e. portion between two trusses Deck Slab panel of size 10.5m x 3m is proposed.
The deck slab panel spans in longitudinal direction, between transverse beams (Top Cross Girders; Main
and Intermediate).
•For supporting panels in cantilever Zone, we have proposed to add bracket beam at all cross girder
Locations. Bracket Beams are double web Box section.
•Between precast panels in-situ concrete will be placed above Top Chord, Cross girders and Bracket; so
as to ensure integrity and continuity of precast panels with the composite steel girders. As all in- situ
concrete is fully supported by Top chord, Intermediate Cross Girder, Main Cross Girder and Bracket,
there is no Staging and formwork is required. This result in saving of times required for erection and
removal of formwork.
Highly Semi
Description Skilled Unskilled Total Officer
Skilled Skilled
Manpower Requirement
4. Use of Mastic and BC for better riding quality and improving life of Wearing Coarse
50mm BC over 12mm Mastic provides better serviceability, riding quality, and life to the wearing than that
conventionally used. Also it provides better water proofing to the Deck Slab and better surface drainage.
5. Launching
Work for Pier Caps for the Sub-structure are not started yet. Delay in this activity can be bottle -neck for
Launching .
Sl.
Month & Year Required Demand (kW) Cumulative Demand (kW)
No
1 March ‘12 100 100
2 April ‘12 150 250
3 June ‘12 100 350
4 August ‘12 250 600
5 October ‘12 300 900