Professional Documents
Culture Documents
An Introduction
Edward Farquharson
March 2011
Contents
• Introduction to the concepts of Value for Money (VfM)
• Conclusions
2
Introduction
• What is VfM?
“The optimum combination of whole-of-life costs and quality (or fitness for purpose) of the
good or service to meet the user’s requirements. VfM is not the choice of goods and services
based on the lowest cost bid.”
• Starting Point:
– Major capital investment options
4
Previous UK Approach
• Numerically based system
5
Technical Adjustments
• Unbundled discount rate - time preference rate of 3.5%
6
Public Sector Comparator
Typical Profile of Net Present Cost of PSC vs. PFI
NPV of PPP
NPV of PPP
cash flows
NPV of PSC
Total value of public sector cash flows
delivering same outputs over life
of contract
– Design and build costs
Risk retained Risk retained
– Operating costs
by Authority by Authority
PSC PPP
7
Public Sector Comparator Methodology
• Policy / legislative context
• Challenges:
– Timing of final output does not help with decision making process
– Reliant on a single-point, cost-based test based on Net Present Values
– Needs empirical data and sector experience (limited at start of programme)
– Reliant on assumptions that can be manipulated (e.g. optimism bias
calculation)
– Danger of double counting
8
UK’s Revised Approach (2006)
A phased assessment conducted in 3 stages:
• Programme level
– Suitability of using private finance
• Procurement level
– A check that procurement will deliver the forecast VfM benefits
9
UK’s Revised Approach – Process (1)
Strategy
Development of departmental capital strategy and programme - Specific investment options identified and appraised - Capital
projects prioritised within Department’s capital programme - areas which may be suited to PFI/ PPP identified
10
UK’s Revised Approach - Process (2)
Does PFI/PPP offer VfM for the project?
Launch Procurement
Financial Close
11
UK’s Revised Approach - Methodology
• Balance between qualitative and quantitative assessment
12
Revised approach - Qualitative Assessment
• Viability
– Measurable and definable outputs, clear scope
– Operational flexibility
– Equity/efficiency reasons for private sector service provision
• Desirability
– Do the benefits outweigh the costs?
• Achievability
– Market interest, time scales
13
Good VfM in PPPs - Enablers
• Definable and contractible outputs
• Competition
14
Good VfM in PPPs - Necessary
• Stable/ defined requirement/ long term need
15
Revised approach - Quantitative Assessment
Identify cost inputs
Adjust for:
• Flexibility
• Tax
• Life cycle investment
16
VfM Analysis – Input Sheet
General
General PFI
PFIFunding
Funding
Timings (Yrs) Rates - Escalators & Discount Rates (%) Base Year Gearing (%) 90%
Timings (Yrs) Rates - Escalators & Discount Rates (%) Base Year Gearing (%) 90%
Contract period 29 CapEx escalator 4.5% 0 Sterling swap rate (%) 5.15%
Contract period 29 CapEx escalator 4.5% 0 Sterling swap rate (%) 5.15%
Initial CapEx period 5 OpEx (non employment) escalator 2.5% 0 Credit spread (bps) 12
Initial CapEx period 5 OpEx (non employment) escalator 2.5% 0 Credit spread (bps) 12
Year when OpEx is first incurred 5 OpEx (employment) escalator 3.5% 0 Bank margin (bps) 100
Year when OpEx is first incurred 5 OpEx (employment) escalator 3.5% 0 Bank margin (bps) 100
Unitary charge escalator 50% 0 Tail for bank debt (yrs) 2
Unitary charge escalator 50% 0 Tail for bank debt (yrs) 2
Real discount rate 3.5% NA Commitment fee (bps) 50
Real discount rate 3.5% NA Commitment fee (bps) 50
Upfront fee (bps) 90
Upfront fee (bps) 90
Costs
Costs Grace period (yrs)
Grace period (yrs)
1
1
Whole Life PSC OB Pre (%) OB Post (%) PFI OB Pre (%)
Whole Life PSC OB Pre (%) OB Post (%) PFI OB Pre (%)
Initial CapEx (£'000)
Initial CapEx (£'000)
65,250
65,250
10%
10%
30%
30%
71,775
71,775
10%
10%
Unitary
UnitaryCharge
Charge
Lifecycle costs at each LC date (£'000) 6,535 10% 30% 1,076 10% Initial CapEx period payment (%) 50%
Lifecycle costs at each LC date (£'000) 6,535 10% 30% 1,076 10% Initial CapEx period payment (%) 50%
Lifecycle intervals (yrs) 10 NA NA 1 NA
Lifecycle intervals (yrs) 10 NA NA 1 NA
OpEx (non employment)(p.a.) (£'000)
OpEx (non employment)(p.a.) (£'000)
1,075
1,075
10%
10%
20%
20%
1,183
1,183
10%
10%
Pre
PreTax
TaxIRR
IRRTargets
Targets
OpEx (employment per person) (p.a.) (£'000) 20 NA NA 20 NA High 18%
OpEx (employment per person) (p.a.) (£'000) 20 NA NA 20 NA High 18%
OpEx (employee number) 25 NA NA 25 NA Medium 15%
OpEx (employee number) 25 NA NA 25 NA Medium 15%
Transaction Low 13%
Transaction Low 13%
Public sector (£'000) 1,958 10% 10% 1,435 10%
Public sector (£'000) 1,958 10% 10% 1,435 10%
Private sector (£'000) 0 0% 0% 1,077 0%
Private sector (£'000) 0 0% 0% 1,077 0%
Third
ThirdParty
PartyIncome
Income PSC
PSC
OB Pre (%) OB Post (%)
OB Pre (%) OB Post (%)
PFI
PFI
OB Pre (%)
OB Pre (%)
Income ( p.a.) (£'000) 475 10% 10% 575 10%
Income ( p.a.) (£'000) 475 10% 10% 575 10%
Flexibility
Flexibility PSC
PSC
PFI
PFI
Scope change year 10 10
Scope change year 10 10
Probability factor (%) 50% 50%
Probability factor (%) 50% 50%
Level of scope change (%) 50% 50%
Level of scope change (%) 50% 50%
Premium flexibility factor (%) 0 10% bps Basis Points
Premium flexibility factor (%) 0 10% bps Basis Points
CapEx Capital Expenditure
CapEx Capital Expenditure
Indirect
IndirectVfM
VfMFactors
Factors PSC
PSC
PFI
PFI
LC
LC
Lifecycle Costs
Lifecycle Costs
Amount (Npv)(£'000) 0 2,000 NA Not Applicable - no input required
Amount (Npv)(£'000) 0 2,000 NA Not Applicable - no input required
OB Pre Pre-FBC Optimism Bias
OB Pre Pre-FBC Optimism Bias
Tax
Tax PSC
PSC
PFI
PFI
OB Post
OB Post
Post-FBC Optimism Bias (for PSC only)
Post-FBC Optimism Bias (for PSC only)
PSC adjustment factor (%) 6% NA OpEx Operational Expenditure
PSC adjustment factor (%) 6% NA OpEx Operational Expenditure
PSC Public Sector Comparator (i.e. conventional procurement)
PSC Public Sector Comparator (i.e. conventional procurement)
Lifecycle
LifecycleRelated
RelatedAdjustments
Adjustments Input required
Input required
PSC lifecycle VfM adjustment 40% Hard-wired Assumption - no input required
PSC lifecycle VfM adjustment 40% Hard-wired Assumption - no input required
Residual cost benchmark 50%
Residual cost benchmark 50%
PSC residual cost factor if lower than benchmark 70%
PSC residual cost factor if lower than benchmark 70%
PSC residual cost factor if higher than benchmark 35%
PSC residual cost factor if higher than benchmark 35%
#END
#END
17
Capturing Non-financial benefits?
•Accelerated delivery: receiving benefits earlier
•Enhanced delivery e.g. better asset condition, design, outcomes
• For renewed schools that were fully rebuilt via a PPP, educational
attainment improved at a rate that was over 90% faster than in fully
rebuilt conventionally financed schools
•Wider societal benefits: e.g. greater cost transparency, procurement
disciplines
18
National Audit Office – Evaluation Matrix
Strategic analysis Tendering Contract Early operational Mature operational
completion
Fit with business Good business case Robust output Clear cut contract Contract being met Service meeting
needs with clear specification requirement
deliverables
Quality of project Design of project Effective team in Contract Post deal evaluation Effective internal
management management place management controls
arrangement
Balance of cost, Affordable based Good quality bids Analysis of Deal remains Benchmarking of
quality and finance on market received financing terms affordable price and quality
soundings
Quality of risk Analysis of scope Risk management Appropriate risk Risk transfer sticks Procedures updated
management for risk transfer procedures transfer agreed
19
Observations
• PPPs can deliver benefits, but not suitable at any price or in every
circumstance.
• PPP projects normally deliver what is asked of them.
• Justifications for PPP may be unclear: use of questionable
quantitative analysis.
• Institutional incentives may encourage the use of PPP.
• Evaluation of PPP: benefits assumptions, comparative data.
• Competition is vital.
• Delivery of real risk transfer depends on a good contract.
• Private finance projects require very careful project management.
• Political will to ensure agreed risk transfer is implemented.
20
Conclusions
• VfM is a concept that compares options
• Affordability and Compliance are constraints
• VfM is important:
– Decision making
– Presentation issues
• The assessment of VfM is a balance between qualitative and
quantitative factors
• UK uses a phased approach (3 stages)
• UK has a standardised quantitative VfM model which
includes various technical adjustments
21