1. Dual Trx Manual Power down Feature Licence Key has to be insatlled in the BSC. 2. Minimum CD level of the BSc should be S12 CD3.1E 3.Flexi 2+2+2 creation in BSC has to create on SEG level instead of BTS level.
ZEQC:BCF=XX,SEG=44, BTS=44:BAND=XXX
2. In 2+2+2 implementation there will be no change in cableing at BTS site, for further expansion there will change in cabling as per the diagram next page.
Configuration at BSC
SEG-1
BTS-1
BCCH BTS-1: TX1 and TX2 on separate antennas BTS-2: TX3 and TX 4 on separate antennas
BTS-2
TRX-3 TRX-4
DTRX 2
TRX-1 TRX-2
DTRX 1
TRX 1 is the BCCH TRX BTS 2 is locked prior to locking DTRX 2 (TRX 3 and 4) using a script *due of antenna hopping in use* TRX 1 and TRX 2 continue to be working on separate antennas with antenna hopping see next slide
2.For 4+4+4 implementation there will be change in cableing as discribed on next page.
Antenna 2
TX 1
TX 2
TX 1 and TX 3 on Antenna 1 TX 2 and TX 4 on antenna 2 DTRX 2 (TRX 3 and 4) to be powered off during low traffic hours DTRX 1 will supply power to DDU TRX 1 will be on Antenna 1 and TRX 2 will be on antenna 2 -> antenna hopping can still be used
Test execution:
Manual power down: Power down TRX(s) with MML command ZERS:BTS=<bts_id>,TRX=<trx_id>:,PD; Manual power up: Power up TRX(s) with MML command ZERS:BTS=<bts_id>,TRX=<trx_id>:,PU;