Professional Documents
Culture Documents
Syllabus
Historical Background Structure of Power System Power Generation Power Transmission
Distribution System
Supplies energy to the consumers At MV/LV levels and Single phase or three phase
Distribution transformers
Not exposed to environmental conditions Inductance is lower in cable so voltage drop is less
But cables are much more costlier than overhead lines for same dispatch capability and voltage
Therefore long distance transmission overhead lines are preferred. Cables are mainly used at distribution levels.
Cables are preferred in following conditions:
Lower losses
Lower switching overvoltages, lower tower clearances No problem of stability and synchronism. Can interconnect systems with different frequencies.
The cost of conductor is expensive item in overhead transmission and this is greatly affected by the choice of the voltage level.
V1 I1 V2 = mV1 I2 = I1 / m
R1
a1
R2 = m2R1
a2 =a1/ m2
There will be a saving in cost of conductor material if the power is delivered at higher voltages.
But higher system voltages will entail more cost of insulation in equipments like transformers, circuitbreakers, and switches. Cost of insulation increases rapidly with increasing voltages. Therefore for certain length of transmission line, the voltage level beyond which it becomes uneconomical.
Therefore, the question is how to select the transmission and distribution voltages?
If C is total annual cost as function of conductor cross section A and working voltage V C = f(A, V)
This will result in most economical conductor cross section and system voltage, if the function f can be defined accurately.
C = annual interest and depreciation on capital cost (fixed cost) + annual cost of energy losses (operational cost). Operational cost depends on conductor cross section, voltage, power factor, change in load time to time, harmonics, etc. Thus, function f depends on many factors and complicated enough to describe it mathematically.
V is the line voltage in kV L is the line distance in km P is the estimated maximum power in kW per phase
Using these empirical relations preliminary estimate is made. Then voltage level is chosen by doing complete economic study of existing interconnected system.