Bihar Infrastructure Company Pvt.Ltd.

5/5/12

Click to edit Master subtitle style

RFP Document's Received for Tariff based bidding from :


1.

2X 660 MW Coal Based Power Project Near Village Pirpainti,Dist Bhagalpur in Bihar (BOO). 2 X 660 MW Coal Based Power Project near Village Chausa Dist. Buxar in Bihar (BOO). 2X 660 MW Coal Based Power Project near village Kajra,Dist Lakhirai in Bihar (BOO).

2.

3.

5/5/12

Seller shall be
1. 2. 3.

Pirapainti Bijlee Company Pvt.Ltd. Buxar Bijlee Company Pvt.Ltd Lakhisarai Bijlee Company Pvt.Ltd.

5/5/12

Requirement:

5/5/12

Clearances already Obtained


1. 2. 3.

Rapid Environment impact study Water Linkage Airport Authority Clearance NOC for 275 M Chimney. Public Hearing Pollution control board Coal linkage is approved for Buxar ,for Pirapainti and lakhisarai it is under progress.(Our Responsibility). 5/5/12

4. 5. 6.

Dates and Schedules :


1.

Pre- Bid Conference is on 30th September 2011. Bid Submission and opening of non financial bid 12th December 2011. Opening of Financial bid 29th December 2012. A bid security bond of Rs. 33.75 Crore for one project, so total amount Rs. 101.25 Crore. Total project schedule is for 41
5/5/12

2.

3.

4.

5.

Location : Lukeesarai

5/5/12

Location : Buxar

5/5/12

Location : Pirpainti

5/5/12

Cost of Land and fuel:


Description Land Pirapainti Rs.0.70 Million per Acre Buxar Rs.0.55 Million per Acre Lakhisarai Rs.0.60 Million per Acre

Fuel (Coal)

Rs.1100 per Rs.1100 per Rs.1100 per MT MT MT 3300 Kcal/Kg 3300 Kcal/Kg 3300 Kcal/Kg

GCV of coal

Cost Ash contentIncluded : Not Included Not Included Not in coal 43% ** of PLF 5/5/12 Transmission : 85%

Power Purchase Agreement:


1.

The procurer plans to procure contracted capacity of 1125 MW at the delivery point as per the terms of PPA. Out of 1320 MW ,100 MW will be for Auxiliary consumption . As per PPA only 1125 will be utilized so an additional (Surplus)95 MW can sold to third 5/5/12 Party.

2.

3.

Extent of Land Requirement:


Description Power Block area Raw water reservoir, all water systems including cooling towers Ash Bund CHS in plant Land for other Facilities Green Belt Housing colony Total Pirpainti 180 Acre 205 Acre Buxar 180 Acre 205 Acre Lakhisarai(Kajra) 180 Acre 205 Acre

365 Acre 210 Acre 40 Acre 325 Acre 85 Acre 1325 Acres

365 Acre 210 Acre 50 Acre 317 Acre 85 Acre 1412 Acres

365 Acre 210 Acre 73 Acre 343 Acre 85 Acre 1461 Acres

5/5/12

Summary of Project Financing: Description Pirpainti Buxar Lakhisarai Total Project Rs.68205.02 Rs.68101.04 Rs.67913.67 Cost MLR MLR MLR Of which Land cost 1111.50 Plant Cost 54836.91 (with taxes & Duties) Prelim & Pre 3325.11 Operative cost Of which 976.00 54880.73 Of which 876.60 54819.14

3326.42

3324.57
5/5/12

Financial Analysis:

Debt Equity Ratio: 70:30 Interest on loan : 11.5 % p.a Interest on working capital : 12% p.a Repayment period : 10 Years Moratorium : 1 year Design life : 25 Years P.L.F : 80 % ; However, its mentioned 85 % else where Auxiliary consumption : 7.5% Plant heat rate : 2150 Kcal /KWh GCV of coal : 3300 Kcal/Kg Cost of coal : Rs. 1100 MT Escalation in fuel cost : 4 % p.a 5/5/12

Conclusion

As per the above project details it is understood that the investment in almost Rs.204219.73 Million out of which considering the 70-30 Equity Ratio a total amount of Rs.61265.919 Million should MPL investment. Plenty of ROW issues has to be done by MPL as a EPC contractor once the award of contract.
5/5/12

As per the bid documents only for BUXAR Thermal Power Project the Procurer has taken the responsibility for obtaining the FSA has been initiated. For other 2 projects the responsibility for FSA is under Procures scope.