11.08.2011 AK
CERC (T&C for tariff determination from renewable sources) Reg. 2009 Applicable
WPD 200 W/m2 & hub height 50 m Small Hydro Biomass Co-gen Solar PV & Solar Thermal
Other states
Plant below 5 MW = 5.50 Cr/MW Plant 5 to 25 MW = 5.00 Cr/ MW
Biomass based generation: Capital Cost for FY 2009-10 - 4.50 Cr /MW Non-fossil fuel based Co-generation Projects: Capital Cost for FY 2009-10 - 4.45 Cr /MW Solar PV Plant: Capital Cost for FY 2009-10 17.00 Cr /MW Solar thermal Plant: Capital Cost for FY 2009-10 13.00 Cr /MW Capital Cost for subsequent years is indexed
Depreciation 7 % of the asset value for repayment period. remaining depreciation (i.e. 20%) spread over remaining useful life of plant. Prorata depreciation for part of the year. Interest on Working Capital Operations & Maintenance expenses (Employee Cost, Repair & Maintenance Expenses, Admin & Gen Expenses) Corporate tax at actual
Interest rate Long term prime lending rate of SBI in previous year + 100 basis point
Biomass based generation: For FY 2009-10 20.25 lakh/ MW & 5.72% escalation/year thereafter Non-fossil fuel based co-generation Plant
For FY 2009-10 13.35 lakh/ MW & 5.72% escalation/ year thereafter
Solar PV generation for FY 2009-10 Rs. 9 Lakh/ MW & 5.72% escalation/ year thereafter Solar thermal generation for FY 2009-10 Rs. 13 Lakh/ MW & 5.72% escalation/ year thereafter
Auxiliary energy consumption 10%
Thereafter 5% escalation shall be considered Fuel Price Indexation mechanism given separately
Sharing of CDM benefits: 1st year 100%, 2nd year 90%, 3rd year 80%, 4th year 70%, 5th year 60%, 6th year onwards 50% of the proceed shall be retained by project developers. Remaining shall be shared by beneficiary.
Solar PV Plant Capacity utilization factor 19% Solar Thermal Plant Capacity utilization factor 23%